Columns
foundations need strengthening in the case of applying additional
loads. Widening and strengthening of existing foundations may be
carried out by constructing a concrete jacket to the existing
footings. The new jacket should be properly anchored to the existing
footing and column neck in order to guarantee proper transfer of
loads. This can be accomplished by drilling holes into existing
concrete of footing and epoxy grouting the longitudinal reinforcement
of jacket. Another possibility is to provide full anchorage
length for longitudinal reinforcement by extending the
column jacket at the top of footing.
When
the bearing area of footing is not sufficient, the size of the
footing should be increased. If the column is also being jacketed,
the transfer of load from column to footing becomes easy. The size of
the “jacket” shall be selected such that the average maximum
foundation pressure does not exceed the recommended allowable value.
Attention shall be given during construction in order that the
excavations for the new “jackets” do not affect the existing
adjacent foundations.
There
can be a split of new concrete from the old concrete surface under
the action of loads. To avoid this splitting of concrete, sufficient
number of closed rings with sufficient overlap or welded connection
should be provided around the footing.
An
isolated footing is strengthened by
increasing the size of the footing and the reinforcement steel bars
as follows:
1.
Excavating around the footing
2.
Cleaning and roughening the concrete surface.
3.
Installing dowels at 25-30cm spacing in both directions using an
appropriate epoxy material.
4.
Fastening the new steel bars with the dowels using steel wires. The
diameter and number of steel bars should be according to the design.
5.
Coating the footing surface with a bonding agent in order to achieve
the required bond between old and new concrete.
6.
Pouring the new concrete before the bonding agent dries. The new
concrete should contain a non-shrinkage material.
If
the bearing area of footing has to be increased without strengthening
of the column, soil pressure on the extended
foundation area has to be transferred
to the existing footing.
Transfer
of soil pressure to existing footing is difficult as
excavation is required below the existing footing.
The building must be properly supported and settlement
of foundation must be avoided.
In
this case also, there is a tendency of the new concrete to split from
the old concrete. To avoid this, sufficient numbers of well
anchored/welded hoops are required.
Thanks for sharing this post!
ReplyDeleteYou've made some pretty good points here
Elcometer 510