ANTI - TERMITE PRE -
CONSTRUCTION CHEMICAL TREATMENT IN BUILDINGS
SCOPE :
This specification covers the general requirements for anti-termite
constructional measures, chemical treatment of soils for the protection of
buildings from attack by subterranean termites, chemicals to be used with their
minimum rates of application and procedure to be followed while the building is
under construction.
APPLICABLE CODES &
SPECIFICATION :
The following codes, standards and specifications are made a part of this
specification. All specifications,
standards, codes of practices referred to here in shall be the latest edition
including all applicable official amendments and revisions. In
case of discrepancy between this specification and those referred to
here in, this specification shall govern:
1. IS : 6313
Part I : Code of Practice for Anti - Termite
Measures
in Buildings
Constructional
Measures
2. IS : 6313
Part II : Pre - constructional chemical
treatment
Measures.
3. IS : 6439 : Specification for Heptachlor
Emulsifiable
Concentrates.
4. IS : 1307 : Specification for Aldrin
Emulsifiable
Concentrates.
5. IS : 2682 : Specification for Chlordane
Emulsifiable
Concentrates.
6. IS : 4015
Part I : Guide for Handling cases of
Pesticide
Poisoning First Aid
Measures.
7. IS : 4015
Part II : Symptoms, Diagnosis and
Treatment.
GENERAL :
The contractor shall furnish all
tools, plants, instruments, qualified supervisory personnel, labour, materials,
any temporary works, consumables, any and everything necessary whether or not
such items are specifically states herein for completion of the job in
accordance with specification requirements.
All work shall be done in the order of
progress required by Owner’s construction programme. The contractor shall take
all necessary precautions to prevent any accident in connection with the
performance of the work. On final
completion of all the work, the contractor shall leave the entire premises
within the site of his operation clean and free from all rubbish resulting from
his operation.
The owner reserves the right to
inspect, check and direct any or all operations at any stage of the work and to
required unsatisfactory work to be remedied at the contractor’s expense. No work
shall be carried out under unsuitable weather conditions viz. when raining or
when the soil is wet due to rain or sub-soil water.
Chemicals shall be brought to site of
work is sealed original containers. The
materials shall be brought in, at a time, in adequate quantity to suffice for
the work. The materials shall be kept in cool and locked stores. The empties shall not be removed from the
work site till the relevant item of work has been completed and permission
granted by Owner / Engineer.
Chemicals available in concentration
forms with concentration indicated on the sealed containers only shall be
used. Chemicals shall be diluted with
water in required quantity before use, using graduated containers to achieve
the desired percentage of concentration:
Examples : Aldrin
20 - 1 lt. is diluted to 40 lts. to
give
0.5% emulsion.
Aldrin
18 - 1 lt. is diluted to 35 lts. to
give
0.5% emulsion.
Chlordane
20 - 1
lt. is diluted to 20 lts.
to
give 1.0% emulsion.
PRE - CONSTRUCTIONAL CHEMICAL TREATMENT :
ESSENTIAL REQUIREMENTS :
Hand operated pressure pump with
graduated containers shall be used to ensure uniform spraying of the
chemicals. Continuous check shall be
kept to ensure that the specified quantity of chemical is used for the required
area during the operation.
CONDITION OF FORMATION :
The treated soil barrier shall be
complete and continuous under the whole of the structure to be protected. All foundations shall be fully surrounded by
and in close contact with the barrier of treated soil. Each part of the area treated shall receive
the specified dosage of chemical.
TIME OF APPLICATION :
Soil treatment shall start when the
foundation trenches and pits are ready to receive mass concrete in
foundations. Laying of mass concrete
shall start when the chemical emulsion has been absorbed by the soil and the
surface is quite dry. Treatment shall
not be carried out when it is raining or soil is wet with rain or sub-soil
water. The foregoing earth surface
within the plinth before laying the sub-grade for the floor.
DISTURBANCE :
The treated soil barriers shall not be
disturbed after they are formed. If by
chance, treated soil barriers are disturbed immediate steps shall be taken to
restore the continuity and completeness of the barrier system.
CHEMICALS, METHOD AND RATE OF APPLICATION :
a.
MOUND TREATMENT :
Termite mounds within the plinth and contingent apron area shall be
destroyed by means of insecticides in the form of water suspension or emulsion
which shall be poured into the mounds at several places after breaking open the
earthen structure and making holes with crow bars. For a mound volume of about one (1) cum, four
(4) litres of an emulsion in water of one of the following shall be used.
i.
0.25 % Aldrin
ii.
0.25% Heptachlor
iii.
0.5% Chlordane
b.
SOIL TREATMENT :
Any one of the following chemical (conforming to Indian
Standards) in water emulsion shall be applied uniformity over the area to be
treated.
CHEMICAL CONCENTRATION BY
WEIGHT %
Aldrin 0.5
Heptachlor 0.5
Chlordane 1.0
TREATED OF COLUMN - PITS, WALL TRENCHES AND BASEMENT EXCAVATION :
a.
The bottom
surface and the sides (up to a height of about 300mm) of the excavation made
for column pits, wall trenches and basements shall be treated with the chemical
at the rate of 5 litres per Sq.M. of the surface area.
b.
After the
column foundations and the retaining walls of the basement come up, the
backfill in immediate contract with the foundation structure shall be treated
at the rate of 15 litre / Sq.M. of the vertical surface of the sub-structure
for each side. If water is used for
ramming the earth-fill, the chemical treatment shall be carried out after the
ramming operation is done by rodding the earth at 150mm centres close to the
wall surface and spraying the chemical with the above done. The earth shall be returned in layers and the
treatment shall be carried out in similar stages. The chemical emulsion shall be directed
towards the concrete or masonry surface of the columns and wall so that the
earth in contact with these surfaces is well treated with the chemical.
c.
In the case
of RCC framed structures with cloumns and plinth beams and RCC basements, with
concrete mix 1:2:4 or richer, the treatment shall start at the depth of 500 mm
below ground level for columns and plinth beams. From this depth the back-fill around the
columns, beams and RCC basement walls shall be treated at the rate of 15 litres
/ Sq.M. of vertical surface. The other
details of treatment shall be as laid down in clause (b) above.
TREATMENT OF TOP SURFACE OF PLINTH FILLING :
The top surface of the filled earth
within plinth beams / walls shall be treated with chemical emulsion at the rate
of 5 lts./Sq.M. of the surface before the sand bed/subgrade is laid. Holes upto 50 to 70mm deep at 150mm centres
bothways shall be made with 12mm dia crow-bar on the surface to facilitate
saturation of the soil with chemical emulsion.
TREATMENT OF JUNCTION OF WALL AND FLOOR :
To achieve continuity of vertical
chemical barrier to inner wall surfaces from the ground level, small channel 30
x 30 mm shall be made at all the junctions of wall and columns with the floor
(before laying the subgrade) and rod holes made in the channel upto ground
level 150mm apart and the chemical emulsion poured along the channel at the
rate of 15 litres / Sq.M. of the vertical wall or column surface so as to soak
the soil right to the bottom. The soil
be tamped back into place after this operation.
TREATMENT OF
SOUL UNDER APRON ALONG EXTERNAL PERIMETER OF BUILDING
The top surface of the consolidated
earth over which the apron is to be laid shall be reacted with chemical
emulsion at the rate of 5 litres / Sq.M. of the surface before the apron is
laid, by making rod holes 75 mm deep at 150mm centres both ways.
These chemicals are usually brought to
site in the form of emulsifiable concentrates.
The containers should be clearly labelled and should be stored carefully
so that children and pet cannot get at them.
They shall be kept securely closed.
Particular care shall be taken to
prevent skin contact with concentration.
Prolonged exposure to dilute emulsions shall also be avoided. Workers
shall wear clean clothing and wash thoroughly with soap and water, especially
before eating and smoking. In the event
of severe contamination, clothing shall be removed at once and the skin washed
with soap and water. If chemicals splash
into eyes they shall be flushed with plenty of soap and water and immediate
medical attention shall be sought.
The concentrates are oil solutions and
present a fire hazard owing to the use of petroleum solvents. Flames shall not be allowed during mixing.
Care shall be taken in the application
of chemicals to see that they are not allowed to contaminate wells or springs
which serve as source of drinking water.
MEASUREMENTS:
The
measurements shall be made in sq.m. on the basis of plinth area of the building
at ground floor only for all operations described above. Nothing extra shall be measured.
RATE :
The rate shall include the cost of all
materials and labour involved in al the operations described above including
making holes and refilling and making good the same.
Excellent information about termite treatment in Building and home, and I home this information will be helpful for me. Thanks
ReplyDeleteAnti termite treatment in Kanpur
Thanks for sharing this information with us and it was a nice blog.
ReplyDeleteBest Pest & Termite Control Service Company in Khammam. We Have Well Trained And Highly Experienced Technicians. Reasonable Prices. 100% Safe Chemicals.
pest control service Telangana
howdy, your websites are really good. I appreciate your work. pest control
ReplyDeleteThanks for sharing this, Such very informative knowledge about Anti Termite Treatment. keep sharing.
ReplyDeleteDo visit here for laboratory glassware manufacturer
ReplyDeleteSchool Science Lab Equipment manufacturers
ReplyDelete